By September 21, the foundation walls were set:

Three courses of concrete blocks make up the foundation. Openings for the garage doors and a small door on the side are left at two courses.


Two weeks later, the slab is poured and cured, and we are ready to begin framing the garage walls.


Next: Framing the Garage Walls Begins