By September 21, the foundation walls were set:
|
|
|
Three courses
of concrete blocks make up the foundation. Openings
for the garage doors and a small door on the side
are left at two courses.
|
|
|
|
Two weeks later,
the slab is poured and cured, and we are ready
to begin framing the garage walls.
|
Next: Framing the Garage
Walls Begins
Return to
the main project Page
|